Fuzzy Logic Project Scheduling Application with Limited Resources on Development Irrigation Project on Java Island

Abstract

On the island of Java, there are many very large areas for agriculture and the development of food crop cultivation such as rice plants, secondary crops, vegetable plants, fruit plants, organic plants, and so on. This area needs an irrigation project from the government to irrigate the crops planted by farmers on the island of Java. This area often experiences floods, land slides, and droughts due to a lack of water. So that agricultural products and food crop cultivation, farmers and the community get optimal results and can be used as a good livelihood for farmers. It is necessary to develop this irrigation project to know the conditions that are very worrying for farmers. So this software was built to solve the problem of allocating renewable resources between activities that have a logical implementation sequence and do not hinder each other which cannot be determined to minimize the function of the makepan project completion time criteria within time parameters, including ready time, duration, time out time, start time and end time are uncertain. The uncertainty of the time parameters is modeled as fuzzy numbers of type I-Left, I-Right, α, β, LR, with three α-cuts {E = 0.5, L=0.8, and I=1.0}. This fuzzy model is transformed into a deterministic model based on three pairs of inferior and superior α-cut values. Activity scheduling priority rules are based on the smallest initial start time value. Resource usage conflicts are resolved in two ways, namely serial and parallel models. The best solution is determined based on the smallest makespan value. Solving this problem involves operations on fuzzy values, including arithmetic operations and relational operations that have certain rules. This software provides two types of schedules, namely optimistic and pessimistic schedules. The result of creating this system is that it can solve the problem of allocation of renewable irrigation resources and renewable resources between activities, which have a logical implementation sequence and do not hinder each other. So, the results can minimize the makespan project completion time in terms of time parameters, including ready time, duration, deadline time, uncertain start time, and end time.

References

  • S. N. S. Sidabutar, M. Amin and Putri, “A Scheduling Production Machine Operations Using The Cds (Campbell Dudek Smith) Method”, At PtTjokroBersaudaraB, 2020.
  • K. S., N. O., “Production Scheduling Of Retreaded Tires Using The Branch And Bound Method And Campbell Dudeck Smith At Cv”, New Nuance. Valtech Journal, vol. 2, no. 2, pp. 108–116, 2019.
  • A. Latief, P. F. Melu, I. H. Lahay and H. Hasanuddin, “Measuring Employee Working Time In Crystal Ice Packaging Using The Time Study Method”, Jambura Industrial Review (Jirev), vol. 1, no. 2, pp. 48–57, 2021.
  • C. Mashuri, A. H. Mujianto, H. Sucipto and R. Y. Arsam, "Penerapan Algoritma Campbell Dudek Smith (CDS) untuk Optimasi Waktu Produksi Pada Penjadwalan Produksi," Jurnal Sistem Informasi Bisnis, vol. 10, no. 2, pp. 131-136, Nov. 2020.
  • M. Sholeh, E. W. Asihand I. Sodikin, “Penjadwalan Pekerjaan Yang Optimal Untuk Meminimasi Keterlambatan Pada Pt Mandiri Jogja Internasional”, Jurnal Rekavasi, vol. 9, no. 1, pp. 35-42, 2021.
  • T. Nuryawan and T. Dwiwinarno, “Standard Time Measurement For Achieving Productivity Case Study Of Making Elementary School Uniforms At Cv”, Focus Production Tamansari, Kalasan, Sleman. Effective Journal Of Economics And Business, vol. 11, no. 2, pp. 133–144, 2020.
  • A. Pranata, “Pemrograman Borl and Delphi, AndiOffset, Yogyakarta”, 2017.
  • R. J. Pressman,“ Software Engineering A Practitioner Approach”, McGrawHill, London, 2017.
  • A. Y. Pradana and F. Pulansari, “Analisis pengukuran waktu kerja dengan stopwatch time study untuk meningkatkan target produksi di PT”, XYZ. JUMINTEN, vol. 2, no. 1, pp. 13-24, 2021.
  • M. Rahayu and S. Juhara,“Measuring Pen Assembling Standard Time Using Downtime Clocks During Work Design Analysis Practicum”, Education And Industrial Applications (Unistek), vol. 7, no. 2, pp. 93–97, 2020.
  • E. M. Sari and M. M. Darmawan, “Measurement Of Standard Time And Workload Analysis In The Filling And Packing Process Of LulurM and iProducts At Pt.Gloria Origita Cosmetics”, Asiimetrik Journal: Scientific Journal Of Engineering & Innovation, vol. 51–61, 2020.
  • P. M. Sari, “Proposed Production Scheduling With The Dudek Smith Campbell Method For Personal Care Products At Pt. Lf Beauty Manufacturing Indonesia”, Journal Of Industrial Engineering Optimization (Joti), vol. 2, no. 2, pp. 60–65, 2020.
  • E. L. Demeulemeester and W. S. Herroelen, “Project scheduling: a research handbook,” Springer Science & Business Media, vol. 49, 2006.
  • D. E. Ezell, “An Analysis of the Program Evaluation and Review Technique (PERT) as a Research and Development Management Tool”, American University., 1968.
  • M. N. Islam, “Crashing project time with least cost: A linear programming approach”, Available at SSRN 1012525, 2004.
  • M. Rondhi, P. A. Pratiwi, V. T. Handini, A. F. Sunartomo and S. A. Budiman, “Agricultural land conversion, land economic value, and sustainable agriculture: A case study in East Java, Indonesia”, Land, vol. 7, no. 4, pp. 148, 2018.
  • S. M. Pasaribu and J. K. Routray, “Performance of farmer-managed irrigation systems for rice production in East Java Province, Indonesia”, International Journal of Water Resources Development, vol. 21, no. 3, pp. 473- 491, 2005.
  • S. C. Sharma, “Operation Research: Pert, Cpm & cost analysis”, Discovery Publishing House, 2006.
  • K. D. Rao, H. S. Kushwaha, A. K. Vermaand and A. Srividya, “Epistemic uncertainty propagation in reliability assessment of complex systems”, International Journal of Performability Engineering, vol. 4, no. 1, pp. 71, 2008.
  • L. A. Zadeh, “Fuzzy logic—a personal perspective”, Fuzzy sets and systems, vol. 281, pp. 4-20, 2015.
  • G. J. Klir and T. A. Folger, “Fuzzy Sets, Uncertainty, and Information”, 1988.
  • M. Z. Muttaqinand and F. Hardaningrum, “Analysis Of Project Implementation Schedule Using Microsoft Project (Case Study: Trenggalek City Square Area)”, IJEEIT: International Journal of Electrical Engineering and Information Technology, vol. 2, no. 1, pp. 25-32,2019.
  • K. M. Sagayam, K. Salahddine, A. A. Elngar and H. M. Ali, “Project Delivery of Goods With Limited Resources and Minimum Time Using Fuzzy Logic Method” Turkish Journal of Computer and Mathematics Education, vol. 12, no. 6, pp. 1729-1740, 2021.
  • P. Coad, E. Yourdonand P. Coad, “Object-oriented analysis”, Englewood Cliffs, NJ: Yourdon Press, vol. 2, 1991.
  • K. Paryati, K. Salahddine, A. A. Elngar and H. M. Ali, “Project Delivery of Goods With Limited Resources and Minimum Time Using Fuzzy Logic Method”.
  • D. Avianda, Y. Yuniati and Y. Yuniar, “Strategi Peningkatan Produktivitas di Lantai Produksi Menggunakan Metode Objective Matrix”, Reka Integra, Vol. 1, no. 4, 2013.
  • R. Kirwan, J. Che, W. J. Le and S. Sarin, “A Visualization and Analysis tool for VCL Auto-generation Code Framework”, In 2021 IEEE International Conference on Service Operations and Logistics, and Informatics (SOLI) (pp. 1-5). IEEE, Dec. 2021.
  • R. W. Sebesta, “Concepts of programming languages”, Pearson Education, Inc, 2012.